
HOME
| WHAT IS
HYDRO |
BENEFITS OF HYDRO |
ROLE OF RENEWABLES | WYRE WYND
|
DAYVILLE
POND |
COLLINSVILLE | PHOTOS |
CONTACT
Collinsville Hydro
Avon - Burlington -
Canton
COLLINSVILLE UPPER AND LOWER
HYDRO PROJECT
The Collinsville upper and lower dams are typical retired New England mill dams.
The upper dam is located in Canton on the Farmington River and the lower is
located immediately downstream in Avon and Burlington, CT. Hydropower at this
location actually began in the late 1700’s when a wooden dam was built near the
current upper dam to power a grist mill. In the early 1800’s the Collins Company
was formed and the extant upper dam and mill building were built in 1837.
Several turbines in the mill building powered the manufacturing equipment. In
1934 the extant upper powerhouse was built on the west end of the dam to utilize
more available flow in the river for electricity production. The lower dam and
powerhouse were built in 1914 to provide additional electricity for the growing
demand. In 1966 both the upper and lower dams and powerhouses were shut down,
retired and donated to CT DEP.
Beginning in 1988 my company, Summit Hydro based in Avon, began the long,
painstaking and costly task of obtaining licenses from the Federal Energy
Regulatory Commission (FERC) for the Collinsville dams in anticipation of
putting them back on line to generate clean, renewable electricity. In the
United States in order to put a hydro facility on line a FERC license or
exemption must first be obtained. The amount of work invested by Summit to
obtain the FERC licenses is almost incomprehensible: hundreds of hours of work,
countless studies, surveys, meetings, correspondences, designs, drawings,
analyses, cash flow statements. Many concerns of agencies, environmental groups,
municipalities and individuals were addressed and mitigated. Summit
submitted the final license applications on September 9, 1989 and, after more
studies and correspondences, the licenses were finally granted on February 23,
2001; it took FERC 11 years to grant
the licenses!
A standard requirement of the licenses is that construction must begin within 4
years of license issuance. Although this seems like ample time, it is known in
the industry, and by FERC staff that it is too short, especially for complicated
projects like the Collinsville. For example, The DEP was positive towards Summit
leasing the facilities, but it took over 3 years to pass the unopposed
legislation that was required to allow DEP to enter leases for the sites. Although Summit
maintained unwavering diligence in obtaining property rights, final designs,
contracts, financing, etc., it unfortunately took more than 4 years and FERC
terminated the licenses on December 4, 2007. Summit did not respond to FERC
regarding the termination nor did we appeal it because there were no good
grounds to argue FERC's decision, it is cut and dry.
However, before the licenses were terminated, Summit
began working with Congressman Murphy’s office on the goal of introducing a bill
to reinstate the licenses back to Summit and extend the construction start
dates. Bills of this nature have been passed before for other licensees that
also had difficulty meeting the tight 4 year time period.
Meanwhile, On February 7, 2008
I met with the Town of Canton First Selectman, Richard Barlow. He explained that
the Town would like to own the projects. (I interpreted it that he wants the
Town and his name showing on a bronze plaque affixed to the powerhouse). I said
that is fine, it’s OK if Town wants to own the project as long as I get paid
fairly for my work and am involved in development. We concluded the meeting with
a handshake understanding that Mr. Barlow will ask the Town Attorney and
Selectmen to put a Letter of Understanding together whereby Summit gets a Bill
passed in Washington which reinstates the licenses back to Summit (the Town uses
its political motivation to help get it passed), then Summit transfers the
licenses to the Town and Summit is compensated fairly for its work expended on
the licenses.
What happened next is rather startling; Canton First Selectman Dick Barlow asked
the Congressman to introduce a bill that would reinstate Summit’s licenses and
transfer them to Canton! The Congressman’s office and Mr. Barlow then turned
their back on Summit and introduced a bill that proposed to pirate Summit’s good
work and give the licenses to the Town. I asked Mr. Barlow if he plans to grab
Summit's licenses, disregard our understanding of 2/7/08 and disavow Summit. He
said "yes".
In 2010, bills HR 4451 and companion bill S 3532 passed
the house then failed in the Senate. Then, in 2011, the
bills were reintroduced as HR 1353 and S 715. These bills also failed. Then, in
2012, HR 5625 has passed the House but not the Senate.
Now, Rep. Esty introduced it
again, HR 316, introduced 1/18/13, and again it has passed the House but not the
Senate. It's the fourth year now that this bill has been introduced. I am
hopeful that there are people in the Senate that read the many letters I have
sent and/or they correctly believe that this Bill is not proper. To see bill
details go to www.congress.gov then type
in "Collinsville" and click the magnifying glass search icon.
In a nutshell, our governmental system has let down a local renewable energy
business. However, there are more important negative aspects of this bill that I
wish to point out. It is unprecedented legislation; the transfer of a FERC
license to a third party without consent of the original licensee has never been
done, thus it will set a negative precedent in the hydro industry which will
tend to deter future hydro development. In addition, this bill will also
circumvent due process. After going through the proper steps, FERC granted the
licenses to Summit, not Canton. Canton has not gone through the proper steps.
In my opinion this proposed legislation is improper and borderline unethical. If
the Town is interested in developing and owning the projects then it would seem
that the first step would be to sit down and discuss it with the local company
that has vast experience and a wealth of knowledge on the projects, Summit
Hydro, rather than taking the current offensive approach.
Unfortunately the hostile approach
has put a wall up between the Town and Summit.
Developing small hydro projects successfully is extremely difficult, time
consuming and risky. At current rates these projects are projected to be
economically difficult. There is no guarantee that these projects will be
feasible. The true economic feasibility will not be known until just before the
shovel is put in the ground.
It is easy to
see the economic difficulty of these projects when examining the development and
operating costs as compared to the income of these relatively small, approximate
1MW, projects. Therefore they should not be
viewed as a source of profit. Incentives from public funds will probably be necessary to
make these projects feasible. However, I believe that, regardless of who
develops the sites, there is a limit at which public funds should not be granted
if the cost per kWh is too high.
Canton has already spent well over
$70,000 of taxpayer money with no explicit payback. I believe that renewables should be encouraged,
but not at any cost.
This raises the question; why
is a town spending its precious resources on the monumental task of developing a
hydroelectric project? Why should taxpayers be put at risk? Other municipalities
have failed at hydro including Woonsocket, RI and Reading, PA. In my opinion
Towns should stay out of the difficult hydropower business and leave it to the
private sector. Towns should stick to their primary responsibilities including
education, planning, zoning, waste water treatment, parks, recreation, library,
roads, senior citizens, etc.
Another point worth noting is that the Collinsville lower project is not located
in Canton. It is located in Avon and Burlington. This raises the question why is
the Town of Canton seeking the license for the lower project which is not
located in Canton?
For further details as to why the proposed legislation should not go forward,
please click here: “Letter
to Blumenthal”.
In my opinion this legislation
is improper and should be either dropped or amended to reinstate the licenses
back to Summit.
More recently, on March 20,
2014, the Town of Canton distributed a Request for Proposals to develop the
project. The RFP states that the developer is responsible for all permits and
costs associated with the project. This lends me to ask; What is the Town
contributing for the project? It looks to me like the Town really doesn't have
much. I would think that anyone wanting to develop the project would simply
begin the process now of filing a FERC license and omit the burden of dealing
with the Town.
In summary, our current stand
on the project is that Summit:
1. Is local to the site and has
a wealth of experience and work done on the project,
2. Would like to see the
project proceed if it can be done without burdening taxpayers,
3. Is not interested in
developing the project by itself,
4. Is currently not wanting to
enter an agreement with the Town due to; a) the negative approach by the Town
regarding abovementioned bill, and b) do not see much value in what the Town can
contribute to project development, and
5. Is willing to help other
private entities develop the project.
Photos of the
Collinsville
Site
Click on any photo to
zoom

Click photo to enlarge,
use back button to return to page |
Summit Hydro owner
Duncan Broatch surveying cross sections in river for Collinsville Lower Fish
Transportability Study, February 28, 1991. |

Click photo to enlarge,
use back button to return to page |
Collinsville Upper Dam
Return to
Top
|
Click photo to enlarge,
use back button to return to page |
Collinsville Upper Power
House
Return to
Top
|
Click photo to enlarge,
use back button to return to page |
Collinsville Upper Forebay
and Trash Racks
Return to
Top |
Click photo to enlarge,
use back button to return to page |
Collinsville Upper
Interior of Power House
Return to
Top |
Click photo to enlarge,
use back button to return to page |
Collinsville Lower Power
House
Return to
Top
|
Click photo to enlarge,
use back button to return to page |
Collinsville Lower Dam
Return to
Top
|
Click photo to enlarge,
use back button to return to page |
Collinsville Lower Trash
racks
Return to
Top |

Click photo to enlarge,
use back button to return to page |
Collinsville Lower Power
House Interior
Return to
Top |
|
|
Photos >>
|